Safety Integrated Basic Functions
10.10 Commissioning the "STO", "SBC" and "SS1" functions
Drive functions
Function Manual, 11/2017, 6SL3097-4AB00-0BP5
713
12
p9621 = "value"
p9622[0...1] =
"value"
Parameterize Safe Brake Adapter.
• Set with p9621 the signal source for the Safe Brake Adapter.
• Set with p9622 the wait times for switching on and switching off the Safe Brake Adapter
relay.
13
p9700 = 57 hex
p9701 = DC hex
Save and copy the Safety Integrated function parameters.
After setting the specific parameters of the Safety Integrated Functions, they must be copied
from the Control Unit into the Motor/Power Module and then activated:
• p9700 SI Motion copy function
• p9701 SI Motion confirm data change
14 p0010 = 0
Safety Integrated: Exit commissioning mode.
• The checksums are checked if at least one safety monitoring function is enabled
(p9601 ≠ 0):
If the target checksum on the Control Unit has not been correctly adapted, then fault
F01650 (SI CU: Acceptance test required) is output with fault code 2000 and it is not pos-
sible to exit the safety commissioning mode.
If the target checksum on Motor Modules has not been correctly adapted, then fault
F01650 (SI CU: Acceptance test required) is output with fault code 2001 and it is not pos-
sible to exit the safety commissioning mode.
• If a safety monitoring function has not been enabled (p9601 ≠ 0), safety commissioning
mode is exited without the checksums being checked.
When safety commissioning mode is exited, the following is carried out:
• A POWER ON must be performed after the initial commissioning. This is indicated with the
A01693 message.
15 p0971 = 1
All drive parameters (entire drive group or only single axis) must be manually saved from
RAM to ROM. This data is not saved automatically!
16 POWER ON
.
After commissioning, a reset must be carried out with POWER ON.
17 -
Carry out acceptance test and create test certificate
.
Once safety commissioning is complete, the commissioning engineer must carry out an ac-
ceptance test for the enabled safety monitoring functions.
The results of the acceptance test must be documented in an acceptance certificate.