Commissioning involves the following steps:
• Basic settings:
If the conv
erter has already been commissioned, then the web server jumps to the basic
settings.
The following settings are required for a brand-new converter:
– Language, date, time
• Security settings:
The settings are congured with the help of the Security Wizard.
You can nd more information in Section "Security settings (Page174)".
• Quick setup:
Menu "Commissioning" > "Quick setup"
– Entry or checking of motor and encoder data
– PTI and PTO conguration
– Limit values and I/O conguration
• Optimize motor:
Menu "Commissioning" > "Optimization"
The Optimization function measures the mechanical drive train using short test signals and
adapts the controller parameters to the mechanics installed.
• Test motor operation:
Action bar > "Control panel"
Test of motor operation using the control panel in jog mode or continuous operation
• Backup:
Menu "Backup and restore"
Siemens recommends a backup of the drive settings after commissioning.
More information
For more information about user management and security settings, seeIndustrial
Cybersecurity Conguration Manual (
https://support.industry.siemens.com/cs/ww/en/view/
109810578).
7.4.2.2 Quick setup
Over
view
The converter can generally be operated without making additional settings using quick setup.
Siemens recommends that you perform the quick setup for the target application.
Requirement
• The drive system has been congured. The components are wired.
• Web server access is active.
Commissioning (web server)
7.4Functions and menus
SINAMICS S200 pulse train servo drive system with SIMOTICS S-1FL2