Series commissioning
8
8.1 Series commissioning
Ov
erview
In series commis
sioning, the backed-up data and settings of a converter are loaded to other
converters.
Requirement
The target converter must satisfy the following prerequisites:
• The rated power of the target converter is the same as the rated power of the converter from
which the backed-up data and settings originate.
• The rmware version of the target converter is higher than or equal to the rmware version
of the converter from which the backed-up data and settings originate.
• The machines that are commissioned via series commissioning are identical in terms of the
application, converter and motor.
• The target converters are all congured to factory settings.
Description of function
There are two options when carrying out series commissioning of the converter:
• Series commissioning with SD card
All settings on the SD card (including user management and access control) are transferred
to the converter.
• Series commissioning using the web server
All settings from the parameter backup (including user management and access control) are
transferred to the converter.
When performing series commissioning, also observe the fundamental principles for
working with the web server (see section "Fundamentals (Page166)").
SINAMICS S200 pulse train servo drive system with SIMOTICS S-1FL2
Operating Instructions, 11/2023, FW V6.3, A5E51646767B AA 221