5
Siemens
A6V12681514_enUS_b
Smart Infrastructure
06/15/2023
Actuator stem extends
Normally open valve closes, normally closed
valve opens
Actuator stem retracts
Normally open valve opens, normally closed
valve closes
NOTICE
The actuator must be commissioned only with a correctly mounted valve in place!
CAUTION
Never intervene manually during self-calibration.
NOTICE
Correct calibration is only possible with valve stroke > 0.05 inch (1.2 mm). Valve stroke
< 1.2 mm results in calibration failure.
If calibration fails, the actuator performs another calibration automatically after
10 seconds.
After three failed calibration attempts, the actuator stem remains in the extended
position and the valves are open.
Power
On
Calibration
Y
t
Fully retracted
Fully extended