6 Connection
SMA Solar Technology AG
Installation ManualMDSEN-US-40-IA-en-1324
• 40mm (1.57in)Peel cable sheath. Make sure that no pieces of cable are dropped into
the inverter.
• Strip off the conductor insulation by 6mm (0.24in).
• On the 2-pole terminal block, unlock the
required terminal positions using a suitable tool
( ) and plug the conductors of the connection
cable into these terminal positions ( ).
Observe the pin assignment.
3. Plug the 2-pole terminal block into pin the row on terminal S0-IN.
4. If no further connections are required on the module or in the inverter, close the inverter and
commission it (see the inverter manual).
5. Configure anemometer or energy meter (see Section7.1, page25).