12.2 Setting up the Service Platform at the Medium-Voltage Switchgear
Compartment
For all work in the medium-voltage switchgear compartment, the service platform must be mounted in front of the
medium-voltage switchgear compartment.
Risk of injury if heavy service platforms are lowered too fast
The service platforms of the MVPowerStation are very heavy. If service platforms are folded down too fast or
dropped, persons could be injured.
Have at least two people pull each service platform forwards and down.
Always wear suitable protective equipment.
Procedure:
1. Open the doors of the medium-voltage switchgear compartment (see Section12.1, page159).
2. Unlock the service platform.
1
2
3. Flip up and lock the support feet of the service platform.
4. Flip down the service platform. Have at least two persons
holding the support feet. This will prevent the support feet in the
locking device from loosening.