SMA America, LLC Commissioning
User Manual BeamBT-eng-BUS110712 35
Establish connection to the devices
37. Move the selection frame to "OK" by turning the button.
The field "OK" becomes dark.
38. Press the button.
The Sunny Beam establishes the connection to the selected inverters and retrieves the data.
When you establish a connection with your PV system through the Sunny Beam for the first time, the
Sunny Beam will retrieve all data for the last two days and the data for the current day. If you are re-
detecting your PV system, the Sunny Beam will retrieve data from the days that have been saved in
the inverter since the last retrieval.
Position Meaning
A The start date and end date of the time period from which the Sunny Beam will
retrieve data.
B The date for which the Sunny Beam is currently retrieving data from the inverters.

Table of Contents