7 Commissioning
7.1 Commissioning Procedure
This section describes the commissioning procedure and gives an overview of the steps you must
perform in the prescribed order.
Procedure See
1. Commission the inverter. Section7.2, page38
2. Establish a connection to the user interface of the inverter.
There are three connection options available to choose
from:
Direct connection via WLAN
Direct connection via Ethernet
Connection via Ethernet in the local network
Section8.1, page43
3. Log into the user interface. Section8.2, page46
4. Configure the inverter. Please note, that the personal
SMAGridGuard code for changing the grid-relevant pa-
rameters must be available after completion of the first ten
operating hours (see "Application for the
SMAGridGuard code" available at www.SMA-So-
lar.com).
Section7.3, page40
5. Ensure that the country data set has been configured cor-
rectly.
Section9.3, page52
6. For PV systems in Italy: Start the self-test. Section7.4, page42
7. Make further inverter settings as needed. Section9, page51
7.2 Commissioning the Inverter
Requirements:
The inverter must be correctly mounted.
The circuit breaker must be correctly rated.
All cables must be correctly connected.
A computer with a WLAN- or Ethernet interface or a tablet PC or smartphone with a WLAN
interface must be available.