Commissioning SMA Solar Technology AG
52 SB20_25_30HF-IEN102911 Installation Guide
7 Commissioning
7.1 Commissioning the Inverter
1. Check for firm positioning on the wall
(see section 4”Mounting the Device” (page16)).
2. Check for correct country configuration
(see section 5.3.2”Checking the Country Standard” (page25)).
3. Check for correct connection of the AC grid cable
(see section 6.2”Connection to the Public Grid (AC)” (page39)).
4. Check for correct connection of the DC cables (PV strings)
(see section 6.3”Connection of the PV Generator (DC)” (page45)).
5. Close unnecessary DC inputs wit the DC plug connectors and sealing plugs
(see section 6.3.4”Connecting the PV Generator (DC)” (page49)).
6. Check whether all enclosure openings are closed.
7. Check whether the enclosure lid is firmly screwed in place.
8. Check for correct connection of the Quick Module.
9. Firmly connect the Electronic Solar Switch.
10. Check for correct design of the line circuit breaker.
11. Switch on the line circuit breaker.
12. If a multi-function relay is connected, switch on the multi-function relay power supply.
Self test in accordance with ENEL directive for initial start-up
(applies to Italy only)
The Italian standard prescribes that an inverter can only operate on the public grid after
the disconnection times for overvoltage, undervoltage, minimum frequency and maximum
frequency have been checked.
If you have configured the Enel-GUIDA country data set, start the self-test as described in
section 7.3”Self-Test in accordance with ENEL Directive, Ed. 1.1 (Applies to Italy only)”
(page54). The test takes approx. 3 minutes.