9.3.11 Assigning Radio-Controlled Sockets
For the following reasons, you must assign the radio-controlled socket to the load to which it is
connected:
• to have the load controlled by the SunnyHomeManager
• to enable the SunnyHomeManager to save the data of the load
If the load was temporarily not assigned to any radio-controlled socket, corresponding data gaps
will appear in the consumption diagrams. The consumption data can always be called up on the
load itself, even if the load is now controlled by a different radio-controlled socket.
Procedure:
• In the drop-down list Radio-controlled socket, select the radio-controlled socket to which
the load is connected. By default, no radio-controlled socket is assigned to the load.
If the desired radio-controlled socket is already assigned to a different load, a "*" will be
displayed in front of the name of the radio-controlled socket. In order to be able to reassign
the radio-controlled socket, you must first remove the assignment of the radio-controlled socket
in the profile of the other load.
9.3.12 Setting Measuring and Switching of the Radio-Controlled
Socket
• In the drop-down list Measuring and switching, select the required setting.
Setting Explanation
Radio-controlled socket is to measure and
switch (intelligent power consumption)
The load draws electric current via the radio-
controlled socket.
Using the consumption values measured by
the radio-controlled socket, the
SunnyHomeManager "learns" how much
power the load typically consumes. This infor-
mation flows into the load control of the
SunnyHomeManager.
Radio-controlled socket is only to switch, not
measure (fixed power consumption)
The load is switched e.g. via a relay which is
connected to the radio-controlled socket.
Using the connected relay, the radio-con-
trolled socket switches the load only in accor-
dance with the configuration (time period)
and the specifications of the
SunnyHomeManager.
The value that is entered in the load profile in
the field Power Consumption is the power
consumption factored in for planning the load
control.
9 Load Control
SMA Solar Technology AG
User ManualHoMan_Portal-BA-en-2084