Fitting the collector sensor
1 Temperature sensor with
heat conducting paste
2 Thermal insulation
3 Roof outlet
(corrugated hose)
4 Process medium
(flow direction)
5 Last collector in flow
direction
6 Collector sensor well
7 Compression fitting
Remote control FE 7
Connection array
Fernb.3
Fernb.1
123
PTC sensor resistance values
The sensors installed in the equipment
(return, flow and DHW sensors), the outside
temperature sensor AFS2 and the contact
sensor AVF6 all have identical resistance values.
Temperature in °C Resistance in
– 20 1367
– 10 1495
0 1630
10 1772
20 1922
25 2000
30 2080
40 2245
50 2417
60 2597
70 2785
80 2980
90 3182
100 3392
PT 1000 collector sensor
resistance values
Temperature in °C Resistance in
– 30 843
– 20 922
– 10 961
0 1000
10 1039
20 1078
30 1117
40 1155
50 1194
60 1232
70 1271
80 1309
90 1347
100 1385
110 1423
120 1461
Fig. 11
26_21_01_0008
Remote control 1
Remote control 3
2.5,8 Sensor installation
The temperature sensors have a decisive
influence on the function of your heating
system. Therefore ensure the correct seating
and adequate insulation of sensors.
Outside temperature sensor AFS 2 (included in
the pack supplied)
Install the outside temperature sensor on a
north or north-eastern wall.
Minimum distances:
2.5 m above the ground
1 m away from windows
and doors. The outside
temperature sensor should
be freely exposed to the
elements, but should not be
installed above windows,
doors or air ducts and
should not be subject to
direct sunlight.
Installation:
- Remove the cover
- Tighten the lower part with screw supplied,
insert and connect the sensor lead
- Replace the cover and let it clearly click into
place
PT 1000 immersion sensor (included in the
pack supplied; only for SOL versions)
Insert the immersion
sensor into the connector
sensor well (see diagram)
Diameter: 6 mm
Length: 1.5 m
The immersion sensor with the
longer silicone lead is the collector
sensor (PT 1000).
The correct connection of the collector sensor
(silicone lead) is crucial to the correct function
of a solar heating system. The sensor on solar
collectors is installed on the last collector,
viewed in the flow direction of the process
medium. For this, install and seal-in the
collector sensor well on the collector. Coat the
collector sensor with heat conducting paste
and insert it into the sensor well tube until it
bottoms out. Provide thermal insulation for
the collector sensor well and the roof outlet,
which must be closed without gap and must
be UV resistant.
Contact sensor AVF 6 (see accessories) This
sensor is required
if a mixer circuit is
installed. Installation
information:
Thoroughly clean
the pipe. Apply heat
transfer paste A, and
secure the sensor
with a cable tie.