The O-ring [10] is attached to the positive pole block [9].
The screws [12] are screwed into the poles.
The O-ring [8] and the insulator [7] are inserted into the base.
The positive pole block [9] is now inserted into the base [5].
The positive pole insulator [1] is put on the positive pole screw [2].
Then the positive pole screw [2] is screwed in.
The positive pole screw [2] fixes the positive pole block [9].
Now the O-rings [3, 4] are attached to the base [5].
The air control ring (AFC) [6] is
put on the base [5] from below.
The O-rings [4] and [14] are attached on the
chamber/chimney [13].
The tank sleeve [11] is put onto the chamber/chimney [13].
Now put the tank on the base [5] and screwed it on.
The O-ring [16] is mounted in the top cap [15].
Now put the top cap [16] on the tank.
The O-rings [18] are attached to the drip tip [17].
Then the drip tip [17] is put into the top cap [15].