EcoInsight I, O & M Guide
Telkonet, Inc.
For Use with Firmware Version 2.x
20800 Swenson Drive, Suite 175
Low Voltage Installation
Waukesha, WI 53186
Revision 4.2
(414) 302-2299
Page 20
www.telkonet.com
Figure 20: Backplate with UL-Rated Insulating Tape
Step 29 Continue to Step 40.
JBOX Using Horizontal Mud Ring Instructions
Requires speed nut that accommodates a #6-32 1” screw.
Requires two #6-32 1-inch screws
Requires 1 hole be drilled into backplate (drilling performed onsite or by Telkonet Production prior to
shipping if requested in advance)
Step 30 Ensure the JBOX has been installed with a horizontal mud ring.
Step 31 Unless this was done prior to shipping, drill a hole in backplate as shown in Figure 21. The
horizontal distance between the hole and the inner right side of the plate should be 1.0”.
The vertical distance between the hole and the inner right side of the plate should be 1
¾”. The hole should accommodate a #6-32 1” screw.
Figure 21: Backplate with Speed Nut and Drilled Hole