Injection Molding Machine Chapter 3
V3.0
3-6
1
Through holes on top of platen.
2
Wire rope does through holes.
3
Operate two 20 tons move cranes simultaneously.
Re-assembly works must be performed by manufacture’s and/or agent qualified personnel.
4 Leveling
Machine must be leveled after installation; unleveled machine has potential risks and can
cause damages both to operator and machine itself.
a. Adjust horizontal level at front side
Check level on tie bars in horizontal direction by level gauge (precision 0.05mm/M), and
adjust mounting pads to have level within 0.2mm/M.
b. Adjust horizontal level at back side