EasyManua.ls Logo

Topline TEC4000 - Page 12

Default Icon
83 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
12
Drawing 9829 REV 101-12-06
Commissioning of the Pool Dosing Equipment
REMOVE THIS AT COMMISSIONING
Commissioning procedure
It is important that the commissioning is comprehensive and complete and leaves no grey areas of
responsibility or accountability.
Clarity of description and explanation of the equipment to the client is therefore vital. Before the
chemical dosing plant is explained, complete the below check list. All of the lines are to be
completed; no blank lines are to be left. If any item is not OK then an explanation must be given.
Commissioning Check list
1.Pool |__________|__________|__________|__________|__________|
2.Positon of controller |__________|__________|__________|__________|__________|
3.Cell / pipework leaks |__________|__________|__________|__________|__________|
4.Cell assembly water flow |__________|__________|__________|__________|__________|
5.Electrical RCCB |__________|__________|__________|__________|__________|
6.Cl / pH / Floc | | | | | |
day & bund tank, position |__________|__________|__________|__________|__________|
7.Cl / pH / Floc | | | | | |
warning labels |__________|__________|__________|__________|__________|
8.Cl / pH / Floc | | | | | |
pump fixing |__________|__________|__________|__________|__________|
9.Cl / pH / Floc | | | | | |
chemical leaks |__________|__________|__________|__________|__________|
10.Cl / pH / Floc | | | | | |
injector position |__________|__________|__________|__________|__________|
11.Electrical Cl / pH / Floc | | | | | |
pump correct pool |__________|__________|__________|__________|__________|
12.Injection Cl / pH / Floc | | | | | |
correct pool, labels |__________|__________|__________|__________|__________|
13.Cl / pH agitator fixings |__________|__________|__________|__________|__________|
14. Secondary flow switch |__________|__________|__________|__________|__________|
15. Site Documentation to | | | | | |
Include HSE, RAMS etc |__________|__________|__________|__________|__________|
16. Site Staff qualifications |__________|__________|__________|__________|__________|
Notes reference above numbers
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________