29
12Test run
Start the system to perform operation check by following the procedure below.
12-1.Preparation
No. Item Details Procedure
1 Preparation Discuss with a customer to determine details of the
following.
• Select devices, and creat a system diagram
• Determine the addresses of an air conditioner and
interfaces, and creat an address management
table
• Set an IP address of Smart Manager with data
analyzer
• Creat a setting file with the Setting File Creation
Software
Refer to the Owner’s manual of the Setting
File Creation Software.
2 Device installation Install Smart Manager with data analyzer and the
interfaces.
Refer to "Installation of the Smart Manager
with data analyzer" (page 12) in this manual.
For further details, refer to the Installation
manual of each device.
3 Wiring Connect the power cables, ground wires, and signal
wires to Smart Manager with data analyzer and the
interfaces.
Refer to "Connection of power cables / earth
wires / communication cables" (page 15) in
this manual.
For further details, refer to the Installation
manual of each device.
4 Device setting Set the air conditioner and the interfaces. Set the address of the devices according to
the address management table.
Refer to "Switches for setting (Smart
Manager with data analyzer)" (page 20) in
this manual.
For further details, refer to the Installation
manual of each device.
1) Air conditioner
Address setting
2) Energy Monitoring
Relay Interface
Address setting, RS-485
termination resistance
setting
3) Digital Input / Output
Relay Interface
Address setting, RS-485
termination resistance
setting
5 Setting file upload
1) Upload the setting file.
For further details, refer to the setting file
creation software.
2) After the change, reset Smart Manager with data
analyzer.
6 Client PC setting Configure network and browser setting of the client
PCs.
For further details, refer to the Network
Configuration Guide of Smart Manager with
data analyzer.