136
MAX 5.9"
(150mm)
MAX 6.
3
"
(160mm)
4.3"
(110 mm)
or more
Spanner push-in part
(Main unit side: 0.67"(17 mm))
Butyl rubber
Spanner push-in part
(Motor side: 0.75"(19 mm))
Spanner push-in part
(Main unit side: 0.63"(16 mm))
Butyl rubber
Spanner push-in part
(Motor side: 0.75"(19 mm))
No.
e
Part name
PMV motor
Procedures
<Cautions at work>
Using spanners by 0.67" (17mm) and 0.75"
(19mm), remove the PMV motor. <AP0243 to
AP0153>
Using spanners by 0.63" (16mm) and 0.75"
(19mm), remove the PMV motor. <AP0123 to
AP0073>
To avoid deformation of the pipes, do not use a
monkey wrench. In case that the clearance to the
ceiling is 4.3" (110mm), use a spanner with length
by 5.9" (150 mm) or shorter.
1) Perform work of item
c
.
2) Perform work of item
d
.
3) Remove the bundling band of PMV motor lead
wire.
4) Pull off butyl of PMV main unit until the position
shown in the right photo.
5) Using a spanner, remove PMV.
<Caution in reassembling>
Determine PMV motor lead wire drawing-out
position as same as that before removing.
Return butyl rubber to the original position.
Remarks
<AP0243 to AP0153>
<AP0123 to AP0073>
f
Horizontal
louver
1) Remove shaft of the horizontal louver from the
back body. (First remove the left shaft, and then
remove other shafts while sliding the horizontal
louver leftward.)