–15–
EN
Hydro Unit
Installation Manual
Tightening
Connect the refrigerant pipes, from the outdoor unit, to the Hydro Unit as shown below.
Align the flare connection on each pipe with the corresponding outlet connection on the Hydro Unit.
Tighten the flare nuts, using fingers, to secure the pipes in place.
Tighten the flare nuts, using a torque wrench, to the tightening torques shown below:
To prevent damage, to the refrigerant pipes, use two spanners to tighten the flare nut connections to the required
torque.
Water Pipe
WARNING
Install water pipes according to the regulations of respective countries.
Install water pipes in a freeze-free place.
Make sure that water pipes have sufficient pressure resistance.
The setting value of the pressure relief valve is 0.3 MPa.
CAUTION
Do not use zinc plated water pipes. When steel pipes are used, insulate both ends of the pipes.
The water to be used must meet the water quality standard specified in EN directive 98/83 EC.
Outer Ø of Copper Pipe (mm) Tightening Torque (N/m)
9.5 33 to 42
15.9 63 to 77
Fig. 7-10
Liquid line Ø 9.52
Gas line Ø 15.88