Exchange of
accumulator
Work procedure
REQUIREMENT
Put on gloves during working; otherwise an
injury may be caused by parts, etc.
Before work, be sure to recover the refrigerant
into a cylinder or the other linked unit so that
there is no refrigerant in the outdoor unit.
1) Remove the lower cabinet (rear side).
2) Take off fixing screws (M6 × 3 pcs.) for
accumulator leg ⇔ base board.
3) Remove the accumulator fixing board ∗ ⇔
fixing screws of accumulator (M6 × 2 pcs.)
∗ The accumulator fixing board is fixed to
the middle partition board.
(Take off the screws only which fix to the
accumulator unit.)
4) Remove the pipe (brazing part) connected
to SV2 valve.
5) Remove the discharge cabinet, fan, and
motor base.
6) Take off the accumulator cover ⇔ fixing
screws (M5 × 4 pcs.) of the middle partition
board, and then pull out it upward.
7) Using a pipe cutter, cut off entrance/exit
pipe of accumulator at the specified posi-
tion. (For the cut-off position, refer to the
Manual attached to the repair parts.)
8) Pull out the accumulator upward.
Remarks