MECHANICAL INSTALLATION
7 - The TES unit should be mounted on a suitable concrete or wooden floor
structure and bolted down utilising the four bolt holes located in the unit base.
(Fixings not supplied)
NOTE: THE UNIT MUST BE SECURELY FITTED TO A FLOOR SURFACE.
FAILURE TO DO SO COULD RESULT IN VIBRATION IN
OPERATION AND STRESSING OF THE CONNECTIONS.
8 - The PVC pipework used for the installation should be glued into the union
tailpieces using suitable PVC primer and cement as recommended by the
pipework supplier.
9 - The connecting pipework adjacent to the TES unit should be adequately
supported to ensure that no additional loadings are put on the reactor union
connections.
10 - The installation of suitable isolating valves is recommended for isolation of
the unit for maintenance and is mandatory if the unit is fitted below the pool
water level.