EasyManua.ls Logo

Unipower UP-2210R - HV 3-Phase Measurement with 3 Cts and 3 Pts (Line-To-Line Voltages)

Default Icon
87 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
UNIPOWER
UP-2210R/P Hardware installation and configuration manual
29
4.4.12 HV 3-phase measurement with 3 CT’s and 3 PT’s (Line-to-line voltages)
Figure 21
The above wiring diagram is used for three-phase measurement in public distribution networks with
3 CT´s and 3 PT’s. The voltage channels of the unit are connected to PT’s (normally 63 V AC
secondary to earth), for supplying line-to-line voltages, and current channels are connected to CT´s
(normally 1 - 5 A AC secondary). Always protect the voltage inputs with a suitable fuse in each
conductor on the secondary side of the PT. The connection for this type of measurement is as
follows:
Channel: Measured object: Channel Measured object:
U1 = L1 PT+ I1+ = L1 CT+
U2 = L2 PT+ I1- = L1 CT-
U3 = L3 PT+ I2+ = L2 CT+
Ref = L1 PT-, L2 PT-, L3 PT- I2- = L2 CT-
I3+ = L3 CT+
I3- = L3 CT-
Note: This configuration is normally used in medium voltage networks.

Table of Contents

Related product manuals