UP-2210R/P Hardware installation and configuration manual
85
2 Check the connection/wiring
2.1
Check nearby equipment (if possible) to ensure that the voltage, current and
power is equal to the measured values in the meter.
2.2
Check vector diagram. The voltage phase sequence should be
U1 red (0°) U2 green (-120°) U3 blue (+120°)
2.3
Check vector diagram. Each current should be within +/-90° from its
corresponding voltage
2.4 Check that PF is >0.7 on all phases as well as total
2.5 Check that P is positive for each phase (if not measuring on a generator)
2.6 Check that unbalance is low (high value means wrong phase sequence)
2.7
Select transfer data a few times. Cancel the transfer and verify that there isn’t a
continuous trigging of sag/swells or transients due to bad settings.
2.8 Erase all old data in the meter
The above points have been discussed:
Date: ____/____- ______
Installation performed by (Unipower representative): Unipower rep. contact information
__________________________________ ______________________________
Installation performed by (customer):
__________________________________