A.9 Checking Clutter Filters with Setup
Mf Command
Test Goal
Verify that the TTY setups for the Clutter Filters section are properly
configured for the
customer application.
Test Equipment
KVM connected
Test Procedure
1. Enter the TTY setups through dspx.
2. Issue the Mf command to display the internal status.
3. Set all the values, as required, for your operation.
Checklist
Table 94 Clutter Filters Setup Checklist
Task Checked OK/Not OK Remarks
Test procedure completed successfully.
Parameters set.
See 5.2.3 Mf — Clutter Filters (page 104).
Test Passed
For Customer Date:
For Vaisala Date:
A.10 Checking General Trigger Setup with
Setup Mt Command
Test Goal
Verify that the TTY setups for the General Trigger Setup section are properly