Sawmill Alignment
Frame Setup
5
5-2 HDSdoc091108 Sawmill Alignment
5.2 Frame Setup
Stationary sawmills should be setup on firm, level ground before proceeding with alignment. Shim
the feet so the weight of the sawmill is evenly supported.
Portable sawmills should also be setup on firm, level ground:
LT40S: Adjust the two middle outriggers on the main frame tube down just enough to lift weight
from the trailer tire.
LT40M: Adjust the two end outriggers on the main frame tube down just enough to lift weight from
the trailer tire.
All Portable Sawmills: Adjust the two outer outriggers down just so they touch the ground but do
not bear weight.
See SECTION 2 Setup & Operation
for additional setup information.
5.3 Blade Installation And Alignment
See Figure 5-1. Install a blade and apply the appropriate tension (See Section 2.4). Blade tension
is adjusted with the tension handle shown.
1. Raise the middle blade housing cover and make sure all persons are clear of the open side of the
FIG. 5-1
SM0243
Blade Tensioner
Gauge
Cant Control
Blade Tensioner
Handle