Sawmill Alignment
Frame Setup
Sawmill Alignment HDSdoc041118 5-2
5
5.2 Frame Setup
Stationary sawmills should be setup on firm, level ground before proceeding with
alignment. Shim the feet so the weight of the sawmill is evenly supported.
Portable sawmills should also be setup on firm, level ground:
LT40S DH: Adjust the two middle outriggers on the main frame tube down just enough to
lift weight from the trailer tire.
LT40M DH: Adjust the two end outriggers on the main frame tube down just enough to lift
weight from the trailer tire.
LT40L DH. Adjust front outriggers on the main frame tube down just enough to lift weight
from the trailer tires.
All Portable Sawmills: Adjust the two outer outriggers down just so they touch the
ground but do not bear weight.
Patrz SECTION 2 Setup & Operation
for additional setup information.