Setup
Install the sweepers and sawhead stops
3
Setup WM doc 12/21/223-11
NOTE: This prevents the
sawhead from sliding up the
mast while mounting it.
See
FIG. 3-12.
5. Raise the sawhead to the upright position.
6. Install the entire head and mast assembly on the bed
rails.
NOTE: Make sure that the
main roller bearings are still
riding smoothly on the rail.
The bearing can be slightly re
adjusted by loosening and
re-tightening the bolts. See
FIG. 3-9.
7. When the carriage and mast are properly aligned,
tighten or re-tighten all bolts in the mast uprights and
the carriages.
8. With the sawhead at the head of the bed, (either end
may be designated as the head) attach two lower seg-
ments of the catch rail. See FIG. 3-13.
9. Move the carriage toward the foot of the bed and install
the last segment of the catch rail, using M10-1.5x30
bolts. See FIG. 3-13.
3.5 Install the sweepers and sawhead stops
1. Install the sawdust rail sweepers on the front sides of
both carriages. Make sure that the sweepers contact the
rails. See FIG. 3-14.
NOTE: Stop blocks must be
attached at both ends, head
and foot, of the track rail to pre-
vent the sawhead from sliding
off the rails.
WARNING!Failure to apply stop
blocks to both ends of the track
rail may result in serious injury
or equipment damage.
Stop Pins
FIG. 3-12
Bolt, M10-1.5x30
Catch Rail
Nut, M10-1.5
Flanged Nylon Lock
FIG. 3-13
Rail Sweeper
Screw, #10x3/4 Sl
Hex Head
FIG. 3-14