(Synchronization mode RUN) [(0&1)&1] RUN synchronization mode will be
enabled.
Notes
For information on the LogicsManager
and its default settings see ╚═▷ “9.3.1
LogicsManager Overview”.
4.4.2.6 Congure Synchronous network
ID Parameter CL Setting range
[Default]
Description
8820 Connect synchronous mains 2 Yes Closing the CBA in case of
synchronous mains is possible if
• System A and System B are
detected as mains connected
and
• The angle is in the conguration
window of parameter 8821 for at
least the time congured in
parameter 8822.
[No] Closing the CBA in case of
synchronous mains (System A and
System B are mains connected) is not
allowed.
Notes
If no closed GCB in the relevant
segment is detected, unloading will be
canceled and the breaker will be
opened immediately (even if the
command “Open CBA with unloading”
is active).
No access in the application mode
A05
.
8852 Connect synchronous segments 2 Yes Closing the CBA in case of
synchronous segments is possible if
• System A and System B are
detected as already connected
and
• The angle is in the conguration
window of parameter 8821 for at
least the time congured in
parameter 8822.
The closing of the CBA is executed
without synchronization.
[No] In case of synchronous segments are
detected, the CBA will not be closed.
Synchronization is not executed.
Notes
No access in the application mode
A05
.
171LS-5 v2 Series37650