Revision A 31
Section 2. Installation
Basic Setup Procedure
See Table 2.1 for a summary of the basic setup procedure and an overall view of the
information in this section. Use the procedure as a quick reference if you are familiar
with the installation requirements for the power supply. If you want more
information, each step in the procedure refers to sections which contain more details.
Execute each step in the sequence given.
Table 2.1 Basic Setup Procedure
Step # Description Action Reference
1 Inspection Perform an initial physical
inspection of the supply.
“Initial Inspection” on
page 32
2 Installation Install the supply (bench or rack
mount); ensure adequate
ventilation.
“Location, Mounting,
and Ventilation” on
page 35
3 Input Power Connect AC input power. “AC Input Power” on
page 36
4 Test Perform functional tests for voltage
mode operation, current mode
operation, and front panel controls.
“Functional Tests” on
page 37
5 Load Connect the load. “Load Connection” on
page 39
6 Sensing Connect sensing lines. “Local and Remote
Sensing” on page 48
TM-XROP-01XN.book Page 31 Monday, March 22, 2004 4:10 PM