2. Installation, Piping, and Wiring
57
TI 11B08A01-01E
3
6
2
17
13
4
18
12
15
14
9
7
10
8
11
1
16
5
Figure 2.2 Accessory kit
Note: The picture is for illustrative purposes only. It is not be an exact representation of each part in the
dimension ratio to the actual one or the number of pieces contained in a kit.
Table 2.2
Item Parts number Quantity Remark
Coil over wrench for LSV L9827EA 1
Seal kit for LSV K9402VG number of LSV Rulon
Seal kit for LSV K9402VH number of LSV Teon
Ferrule J9218VU 1 set For capillary column
Ferrule J9218VT 1 set For megabore column
Cutter J9218VV 1 For megabore or capillary column
User’s manual (CD) 1 IM 11B08A01-51E
Operation data 1
GCUD (CD) K9809AA 1 For user programming option
Manual K9809AN 1 For GCUD
(5) Installation
Useanchorboltstosecuretheself-standingtypeanalyzerontheoor.Aftertheinstallation,
removethexturebrackets.
Use nuts and bolts to secure the wall-mounting type analyzer on the wall. The wall construction
has to be designed to withstand four times the analyzer’s own weight.
For the hole for installation, refer to “1.2 External Dimensions.”
2.1.2 Installing Auxiliary Hardware
(1) Cylinders
The following conditions must be met:
(a) Located near the analyzer or the external sampling system.
(b) Not subject to rainfall or direct sunlight
(c) Ambient temperature: 0 to 40°C
(d) The place should be well-ventilated so that leaking gases, if any, do not accumulate.
Comply with regulations for high-pressure gases.