46
3.2.6 Check bias interconnection _____________________________________________
3.2.7 If required check 3 phase tripping_______________________________________
3.2.8 On load tests
Load conditions
Measured differential current __________ __________ __________ A
3.2.9 Magnetizing current inrush test _________________________________________
_________________________________ __________________________________
Commissioning Engineer Customer Witness
_________________________________ __________________________________
Date Date