13 Installation
P15D/EN TM/B
13-7
Before Energizing following should be checked
1. Voltage rating and polarity.
2. CT circuit rating and integrity of connection.
3. Protective fuse rating.
4. Integrity of the earthing connection.
5. Voltage and current rating of external wiring, applicable as per application.
Relay Operating Condition
The equipment should be operated within the specified electrical and environmental limits.
Current Transformer (CT) Circuit
Do not open the secondary circuit of a live CT as the high voltage produce may be lethal to personnel
and could damage insulation. Generally, for safety, the secondary of the line CT must be shorted
before opening any connection to it.
Insulation and dielectric strength testing
Insulation testing may leave capacitors charged up to a hazardous voltage. At the end of each part
test, the voltage should be gradually reduced to zero, to discharge capacitors, as this may result in
damage.
2.1.1 Cables and Connectors
This section describes the type of wiring and connections that should be used when installing the
device. For pin-out details please refer to the wiring diagrams.
Caution: Before carrying out any work on the equipment you should be
familiar with the Safety Section and the ratings on the equipment’s
rating label.