HydroLift
Installation and initial commissioning
9.1 Make lifting units operational
1. Turn off all lifting units and the main switch.
2. Open the cover.
3. Top up oil. ( 11.5)
4. Insert and connect batteries. ( 11.9)
5. Bleed the lifting unit. ( 11.4)
6. Check oil level. (refill if necessary) ( 11.3)
7. Remove transport lock [6].
8. Adjust the ground clearance of the chassis
with screw [7].
9. Close cover and screw down.
10. Charge the batteries. ( 10.9)
Steps 1 to 10 must be repeated for all lifting units.
Steps 3, 4, 5 and 6 are only necessary if the lifting
units have been delivered without oil and batteries.