19 | P a g e
vertical bracket comfortably horizontally.
At least 3 feet above the ground. Hang the control on the bracket.
Mounting the Flow Switch, and Cell.
Flow switch, confirm that the arrows on the flow switch (located on the
side) point in the same direction of water flow.
The Cell and Flow Switch cables have easy plug-in connectors in the
control, the diagram below for the location of these connections.