EasyManua.ls Logo

Bray Flow-Tek Triad Series - 8.6 Installation of Weld-end (Non-Extended) Valves

Default Icon
35 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
TRIAD SERIES 3-PIECE BALL VALVE
Installation, Operation, and Maintenance Manual
 of ©  BRAY INTERNATIONAL INC ALL RIGHTS RESERVED BRAYCOM The Information
contained herein shall not be copied transferred conveyed or displayed in any manner that would
violate its proprietary nature without the express written permission of Bray International Inc
Follow the appropriate welding procedures per the applicable
industry standards that are compatible with the valve and piping
materials being joined While welding monitor the valve body
temperature near the seat pockets using a temperature indicator
stick ensuring that the temperature does not exceed C
(F)
After welding follow the appropriate post weld heat treatment
(PWHT) procedures per the applicable standards PWHT shall
be performed localized To avoid excessive body temperatures
perform PWHT to one end of the valve and then normalize to
ambient temperature before proceeding to the second end of the
valve
After installation with the valve still in the open position flush
the piping system and valve clean again to remove any dirt burrs
and welding residue that may have accumulated during valve
installation
After installation and flushing of the piping system verify smooth
operation by cycling the valve several times
 Installation of Weld-end (Non-Extended) Valves
NOTICE
Ensure that appropriate weld procedures are implemented that
are compatible with the materials used
 Ensure that the piping and valve end connections are
properly aligned to avoid line bind
 Tack weld the valve to the pipe at four points on both end
caps
 With the valve in open position (the valve is in the open
position when the handle is parallel to the axis of the valve
and pipe) loosen all body bolts remove the body from
between the end caps
 Turn the handle in the half open position to assist in the
removal of the seats and inner body gaskets
 Turn handle in closed position and remove ball
 Place all removed parts in a clean and secure place
 Replace the body and all body bolts and tighten them hand
tight This operation is very important so that the body
and end caps remain perfectly parallel thus preventing any
leakage at the body joint after welding
 Apply a welding ground strap adjacent to the valve end being
welded to prevent current flow through the valve