7
NOTES: 
1. Unit weights (shown  in  pounds),  ±  10  percent, are based on the
largest water-filled coil.
2. The  operating  weight  information  is  based  on  8-row  water-filled
coils and double wall cabinet construction. For a different coil and
cabinet options, use the weight adjustment table (Table 1).
Fig. 7 — 42DV Vertical Unit — 
Weight Distribution Calculations
Step 2 — Install Mixing Box
1. Mixing boxes are pre-assembled from the factory for ease of
installation.  A  linkage  kit  consisting  of  two  crank  arms,
2 swivels, and either a 25 in. (sizes 06-16) or a 34 in. (sizes
20-30) length of 5/16 in. rod is provided for field-installation
of an actuator. Mixing boxes are only compatible with side/
bottom  (horizontal  units)  and  side/top  (vertical  units)
access-style filter frames (non-magnetic latching doors). See
Fig. 14 for dimensional information.
2. Assemble  the  base  rails  (provided  with  mixing  box.  (See
Fig. 8.) All hardware required for assembly is included  and
the  base  rails  are  letter  coded  for  ease  of  assembly.  (See
Fig. 9.)
Fig. 8 — Base Rails
Fig. 9 — Letter Coding on Base Rail Parts
PLACE UNIT ON THE BASE RAILS
42DH- Horizontal Units
Unit is mounted flush to the outer edge of the end base rail at the
aligning unit mounting holes. (See Fig. 10.) It may be necessary to
remove factory installed sheet metal screws to enable access to all
mounting holes  and to ensure proper fit. Do  not remove  screws
unless necessary. Secure unit to base rail using No. 8 x 1/2 in. fas-
teners at the locations shown in Fig. 9 and 10. Use two fasteners
per side.
42DV UNIT
NO ELECTRIC HEAT (lb)
A B C D Total
06 76 38 35 42 191
08 85 39 37 38 199
10 78 45 44 78 245
12 84 45 46 80 255
16 85 74 62 82 306
20 90 84 77 88 339
22 110 90 73 90 363
30 147 140 113 128 528
42DV UNIT
WITH ELECTRIC HEAT (lb)
A B C D To
tal
06 85 40 44 49 218
08 94 48 44 47 234
10 86 58 55 84 283
12 97 62 58 92 309
16 105 79 70 92 346
20 111 88 81 99 379
22 133 88 92 99 412
30 160 140 131 137 568