Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53230016-01 Printed in U.S.A. Form 23XRV-8SI Pg CL-1 6-22 Replaces: NEW
INSTALLATION START-UP REQUEST CHECKLIST
Machine Model Number: 23XRV _______________________________ Serial Number:
To: Date:
Project Name:
Carrier Job Number:
Attn.:
The following information provides the status of the chiller installation. Send a copy of this checklist to the local Carrier Service office
after it has been completed and signed off by the Purchaser and Job Site Supervisor.
(YES/NO/N/A) DATE TO BE
COMPLETED
1. The machine is level within 1/2 in. end to end.
2. The machine components are installed and connected in
accordance with the installation instructions.
3. The isolation package and grouting (if necessary)
are installed.
4. The relief valves are piped to the atmosphere.
5. All piping is installed and supported. Direction of flow
is indicated in accordance with the installation instructions
and job prints.
a. Chilled water piping
b. Condenser water piping
c. Waterbox drain piping
d. Pumpout unit condenser piping (if installed)
e. Other
6. Gauges are installed as called for on the job prints required
to establish design flow for the cooler and condenser.
a. Water pressure gauges IN and OUT
b. Water temperature gauges IN and OUT
7. The machine’s control center wiring is complete. The wiring is
installed per installation instructions and certified prints.
a. Power wiring to VFD circuit breaker. (If chiller was
disassembled during installation, motor leads must
not be taped until the Carrier technician megger tests
the motor.)
b. Can the water pumps be energized from Carrier controls?
Note this can be accomplished through BMS interlock with
Carrier controls (typically via BACnet or Modbus) or hardwire
connections to pumps. Chiller must maintain pump control for
freeze protection purposes. If answer no to this question customer
must sign off since this can result in loss of warranty coverage.
c. Line side voltage is within ±10% of chiller nameplate voltage.
d. Other
NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere
to the safety considerations/information as outlined in preceding
sections of this Installation Instructions document.