D-EIMWC01008-16_03EN - 21/35
5.8 Before Starting
The unit should not be started, not even for a very short period of time, before the following pre-
commissioning checklist is filled out completely.
standard steps to go through before starting the unit
Check for external damage.
Open all shut-off valves.
Install main fuses, earth leak detector and main switch. Recommended fuses: aM
according to IEC standard 269-2.
Refer to the wiring diagram for size.
Supply the main voltage and check if it is within the allowable ±10% limits of the
nameplate rating.
The electrical main power supply should be arranged so, that it can be switched on or
off independently of the electrical supply to other items of the plant and equipment in
general.
Refer to the wiring diagram, terminals L1, L2 and L3.
Supply water to the evaporator and verify if waterflow is within the limits as given in the
table under “Water charge, flow and quality”.
The piping must be completely purged. See also chapter “Preparing, checking and
connecting the water circuit”.
Connect the pump contact(s) in series with the contact of the flow switch(es), so that
the unit can only come in operation when the water pumps are running, and the water
flow is sufficient.
Check the oil level in the compressors.
Install the filter kit(s) supplied with the unit in front of the evaporator(s) water inlet.
Check that all the water sensors are correctly fixed into the heat exchanger (see also
the sticker attached to the heat exchanger).
It is necessary to read the operation manual delivered with the unit before operating the
unit.
It will contribute to understand the operation of the unit and its electronic controller.
Close all switch box doors after installation of the unit.