5.1.2 Safety measures
5.1.2.1 TM safety measures fully comply with safety measures stated
in item 4.3.1 of the present OM.
5.1.3 Maintenance procedure of the dosimeter
5.1.3.1 External examination
External examination of the dosimeter should be performed in the
following order:
- check the technical condition of surface, inspect for integrity of seals,
absence of scratches, traces of corrosion, surface damage of the dosimeter;
- check the condition of clamps in the battery compartment.
5.1.3.2 Delivery kit completeness check
Check if the delivery kit is complete according to Table 3.1.
5.1.3.3 Operability check of the dosimeter.
5.1.3.3.1 Operability check of the dosimeter is performed
according to item 4.2.4 of the present OM.