Description and Technical Data:
Regulators are used to avoid permanent on/off
cycling of compressor or to keep evaporating
temperatures above certain levels
• Can be installed in any position.
• Intended for use with CFC, HCFC, HFC
• Adjustable from: CPHE -0,4 to 5 bar
• ACP: 0 to 5 bar
• Factory setting: CPHE: 1,4 bar
• ACP: 2,7 bar
• Max. allowable pressure PS: CPHE: 35 bar
• ACP 31 bar
• Medium temperature range TS: -40°C to 120°C
• Ambient temperature range: -40 to 50°C
• Transport temperature range: -40 to 70°C
• Marking:
•
Safety Instructions:
• Read installation instructions thoroughly.
Failure to comply can result in device failure,
system damage or personal injury.
• It is intended for use by persons having the
appropriate knowledge and skill. Before
attempting to install the regulator, make sure
pressure in system is brought to and remains at
atmospheric pressure.
• Do not release any refrigerant into the
atmosphere.
• Do not use any other fluid media without prior
approval of Alco Controls. Use of fluid not
listed could result in change of Hazard
Category of the product and consequently
change of conformity assessment requirement
for product in accordance with European
Pressure Equipement Directive 97/23/EC.
• In a severely contaminated system, avoid
breathing acid vapours and avoid contact with
skin from contaminated refrigerant / lubricants.
Failure to do so could result in skin injury.
• CPHE and ACP are not released for use with
flammable refrigerants such as hydrocarbon
refrigerants and ammonia.
• The CPH(E) regulator’s power assembly and
cage assembly must be removed before
soldering.
Installation and Mounting:
Two typical installation applications are possible:
Hot Gas Bypass to the evaporator inlet (with up to
100% of capacity control) per Fig. 1
Hot Gas Bypass to the suction line (max. 40% of
capacity control because of oil return
capability) per Fig. 2
• Pressure regulators can be installed in any position.
• Direction of flow must match arrow on body.
• Before brazing clean tubing.
• CPHE: Remove power assembly and cage before
brazing.
• ACP: Do not disassemble valve before brazing.
•
Use wet rags or chill blocks when brazing to
Direct flame away from valve body (Fig. 3).
Use an inert gas such as nitrogen to pass through
The use of appropriate brazing material is required
(soft solder is not allowed).
Internal parts must be protected from foreign
material and moisture. ALCO filter
liquid line and ALCO filter use in suction line is
Install the external equalizer line to the compressor
pressure regulators. NEVER join the equalizer line
with another control except of the Liquid Injection
If desired set point differs from factory setting,
follow the procedure for setting before any
The function of the CPHE and ACP series regulators
is to prevent the suction pressure from falling below
a predetermined set point, thereby balancing the
system. Therefore, the first step after installation is
to determine this set point for the minimum suction
pressure allowable for your application. To do so,
Start the system and determine if it is operating
properly. Install a gauge on the compressor suction
line and measure the suction
system has stabilized. To make sure, that hot gas is
Remove the seal cap (1) and turn the power
assembly adjusting stem (2) full
Reduce the evaporator load until the sucti
pressure lowers to the point at which bypass is
Energize hot gas solenoid to enable gas flow.
Turn the power assembly adjusting stem on top of
the regulator in a CLOCKWISE direction until
bypass occurs and suction pressure does not fall
CLOCKWISE turn of the adjusting stem will
increase the pressure setting; a
COUNTERCLOCKWISE turn will decrease it.
Adjustments should be made in small increments,
allowing the system to stabilize after each turn.
regulator (only CPHE). This screw should only be
used when working in a vacuum temperature range
Vary evaporator load to test at various conditions
that the suction pressure does not fall below the
CPHE: Replace the seal cap (1) on the adjusting
DWG Nr.: CPH EZ 005000/PCN 863003
Emerson Climate Technologies GmbH
Germany
www.emersonclimate.eu
Use wet rags or chill blocks when brazing to
exceed max. body temperature of 120°C.
Direct flame away from valve body (Fig. 3).
Use an inert gas such as nitrogen to pass through
The use of appropriate brazing material is required
(soft solder is not allowed).
oxygen or flammable gases.
Internal parts must be protected from foreign
material and moisture. ALCO filter
liquid line and ALCO filter use in suction line is
Install the external equalizer line to the compressor
ays downstream from evaporator
pressure regulators. NEVER join the equalizer line
with another control except of the Liquid Injection
If desired set point differs from factory setting,
follow the procedure for setting before any
n and/or refer to the Adjustment Table
The function of the CPHE and ACP series regulators
is to prevent the suction pressure from falling below
a predetermined set point, thereby balancing the
system. Therefore, the first step after installation is
to determine this set point for the minimum suction
pressure allowable for your application. To do so,
Start the system and determine if it is operating
properly. Install a gauge on the compressor suction
line and measure the suction
system has stabilized. To make sure, that hot gas is
-energize the hot gas solenoid.
Remove the seal cap (1) and turn the power
assembly adjusting stem (2) full
Reduce the evaporator load until the sucti
pressure lowers to the point at which bypass is
Energize hot gas solenoid to enable gas flow.
Turn the power assembly adjusting stem on top of
the regulator in a CLOCKWISE direction until
bypass occurs and suction pressure does not fall
he predetermined set point. A
CLOCKWISE turn of the adjusting stem will
increase the pressure setting; a
COUNTERCLOCKWISE turn will decrease it.
Adjustments should be made in small increments,
allowing the system to stabilize after each turn.
turn adjustment screw on the side of the
regulator (only CPHE). This screw should only be
used when working in a vacuum temperature range
Vary evaporator load to test at various conditions
that the suction pressure does not fall below the
CPHE: Replace the seal cap (1) on the adjusting
On multiple evaporator systems, do not pipe hot
gas to more than one evaporator. Use separate
bypass regulators or consult the ALCO
Applications Engineering De
If the compressor is located above the evaporator,
bypass should be piped to the evaporator to insure
proper oil return during low load bypass
On a long piping run, bypass to the evaporator,
insulate the bypass to prevent condensate.
Condensate can lead to unstable conditions and
or flooding of the compressor.
If a compressor discharge line thermostat is used,
it is recommended that the solenoid
series with the thermostat.
Voltage and frequency of the c
to the power source. Connect leads to the power
(NEVER wire on the load side of the motor
Note 1: For installation of a Liquid Injection Valve
series), refer to ALCO’s catalog for selection
injection solenoid valve is used,
the electrical connections should be in parallel with
the hot gas solenoid valve.
After completion of installation, a pressure test
must be carried out as follows:
According to EN378 for systems which must
comply with European pressure equipment
To maximum working pressure of system for
Failure to do so could result in loss of refrigerant
ressure test must be conducted by skilled
persons with due respect regarding the danger
Before any service shut down system and
disconnect from power source.
Fully depressurize regulator. After reducing
be opened, internal parts removed, cleaned and
replaced, per Fig.4. Install parts in reverse
Replace gaskets 4, 6 and 7 before reassembling the
Tighten capscrews evenly to torque specification
DWG Nr.: CPH EZ 005000/PCN 863003
Emerson Climate Technologies GmbH
On multiple evaporator systems, do not pipe hot
gas to more than one evaporator. Use separate
bypass regulators or consult the ALCO
Applications Engineering De
If the compressor is located above the evaporator,
bypass should be piped to the evaporator to insure
proper oil return during low load bypass
On a long piping run, bypass to the evaporator,
insulate the bypass to prevent condensate.
Condensate can lead to unstable conditions and
or flooding of the compressor.
If a compressor discharge line thermostat is used,
it is recommended that the solenoid
series with the thermostat.
Voltage and frequency of the c
to the power source. Connect leads to the power
(NEVER wire on the load side of the motor
Note 1: For installation of a Liquid Injection Valve
series), refer to ALCO’s catalog for selection
injection solenoid valve is used,
the electrical connections should be in parallel with
the hot gas solenoid valve.
After completion of installation, a pressure test
must be carried out as follows:
According to EN378 for systems which must
comply with European pressure equipment
To maximum working pressure of system for
Failure to do so could result in loss of refrigerant
ressure test must be conducted by skilled
persons with due respect regarding the danger
Before any service shut down system and
disconnect from power source.
Fully depressurize regulator. After reducing
be opened, internal parts removed, cleaned and
replaced, per Fig.4. Install parts in reverse
Replace gaskets 4, 6 and 7 before reassembling the
Tighten capscrews evenly to torque specification
Библиотека СОК