Throughthe Wall InstallationInstructions-OptionaL
Thecasemay be installed throughthe wall in bethexistingand new construction.
Readcompletely, then follow step-by-step.
IMPORTANT
Throughthewall installation is notappropriate
if anyof theside louversin the case will be
obstructedby the wall.
All side louversin the casemustproject on the
outdoorside of thewall.
Theroomside ofthe casemustproject intothe
roomat least 13/g"fromthe finished wall.
Thecasemustbe installedlevel fromside-to-side
and with a slighttilt fromfront to rear. Usea level;
abouta 1/2bubblewill be thecorrectcaseslantto
theoutside.
[]Remove the air conditioner from the case.
For specific instruction, refer to the Window
Installation Instructions.
[]Make certain a walt receptacle is available
close to the hole location or make
arrangements to install a receptacle.
[]Place the case in the wall opening and
secure with 12 1" long #10 wood screws.
NOTE:Drill pilot holes, if necessary, for proper
installation. If the frame is oversized, use shims
toprevent case distortion.
Finish the Wall Open&g
Caulk all four sides on the outdoor side of the case to prevent moisture from getting through to the
interior walt. Use of flashing (drip rail) will further prevent water from dripping inside the wall and
down the outside of the building.
[-P,aster,loe
Lnteange(frequred)_:l _//
Caulking _111 -- Trimmolding(if,desired)
OUTSIDE
Air louvers
(must project on
the outdoor side
of the wall,)
Wood Filler and Caulkir
(above & below the flashing)
Flashing (Drip rail)
INSIDE
..I Bottom rail
4,5 cm (13/4") min.
15