GREE                                                                                                    U-Match 5 SERIES UNIT SERVICE MANUAL
 
87 
 
Note: Before removing the condenser, make sure there is no refrigerant in the pipeline and power is cut off. 
5. Take out the condenser.   
●Loosen the securing screws of 
condenser support. Take off the 
plate type heat exchanger and the 
support as a whole.   
6. Install the new condenser.   
●Secure the screws of condenser 
and support. Then fix them 
together on the chassis.   
●Install the condenser by referring 
to the positions of entering and 
leaving pipes. Weld the connection 
pipes.   
●Nitrogen welding: the pressure of 
nitrogen is 0.5±0.1kgf/ c  ㎡ 
(relative pressure). Note: When 
welding the pipes, do not let the 
flame burn the other components.   
7. Secure the electric box and 
arrange the wires according to the 
requirement.   
●Put the electric box in place and 
tighten up the screws of electric 
box.   
●Arrange and secure the wires as 
original.     
8. Check and open the upper and 
side panels.   
●Check whether each component 
and connection wire is well 
connected.   
●If everything is OK, place back 
the upper, left and right side 
panels.