GREE U-Match 5 SERIES UNIT SERVICE MANUAL
116
Removal of electronic expansion valve
Note: Before removing the electronic expansion valve, make sure there is no refrigerant in the pipeline and power is cut off.
Step Picture Work instruction
5. Install the new electronic
expansion valve.
Weld the connection pipe of
electronic expansion valve.
When welding the electronic
expansion valve, the valve
should be wrapped with wet
cloth.
Nitrogen welding: the pressure
of nitrogen is 0.5±0.1kgf/ c
(relative pressure).
Note: When welding the pipes,
do not let the flame burn the
other components.
Install the coil of electronic
expansion valve.
6. Secure the electric box and
arrange the wires as required.
Put the electric box back in
place and tighten up the
screws.
Arrange the wires as original.
7. Check and install the panels.
Check whether each
component and connection
wire is well connected.
If everything is OK, install the
upper, left and right panels.
Tighten up the screws.