3. Assembly and installation procedure HIRO 160 Q
11
Align the guide rails in all directions using the spirit
level.
The lift unit drawing shows the height dimensions
at each join position between the guide rail beams.
Compare the clearance dimensions and the height
dimensions with the actual dimensions at the
installation site, and if necessary, adjust the guide
rail track.
To lay the charging cables, use a coiled cable or
the cable supplied.
After installing the first guide rail beam,
the charging cable must be laid inside the upper
guide rail tube.