Transport the product as close to the installation location as practical before unpacking.
Do not put any material on the product during transportation.
Confirm the number of parts by referring to the model printed on the package before unpacking.
Check that no foreign materials are inside the parts before fixing work.
Cut the end of the pipe to meet with the specified pipe size as shown in the figures.
Locate branch pipes on the same horizontal plane with minimum straight length after vertical bend.
Secure pipe ends with caps when passing through walls and avoid direct ground contact.
Ensure stop valves are closed and blow pipes with nitrogen when brazing.
Check for refrigerant leakage and attach insulation to all branches and field piping.
Connect liquid piping with 9.53mm size for units 2HP or smaller and piping over 15 meters.
Perform insulation when piping temperature decreases and cap open ends to prevent moisture intrusion.