Commissioning
It is essential that the following points are completed by the Heating
Engineer before commissioning is requested through Hoval.
System full of water and vented
Boiler ue box drain pipework is tted
Spirals tted where appropriate
Heating load available e.g. pumps working
Fuel purged to burner isolation valve
Oil bled to boiler isolation cock
Electrical connections made and correctly fused
Correct boilerhouse ventilation
Other manufacturer's equipment has been installed
& commissioned as necessary, e.g. pressurisation units.
If the above are not completed and commissioning is unable to
commence, clients will be charged for the abortive visit.
Hoval Service Engineers normally commission all new
boilers and they will check the following:
the boiler and system is lled with water and vented, including circulation pumps.
the boiler ue box drain pipework is tted.
an independently pressurised system is operating correctly. Suppliers of the equipment
should adjust their equipment during commissioning.
that dampers in the flue between the boiler and the chimney (if fitted) are in
the open position and locked open if manually operated and if electrically operated that the
burner is interlocked electrically to prevent operation until the damper is open.
the electrical installation with the appropriate wiring diagram for the boiler and burner and for
correct fan rotation.
correct direction of ow in the gas line.
correct operation of the gas booster (if tted)
on oil burners that a lter and exible oil supply pipe-line is tted.
the burner has not been damaged in transit or during installation and that it is a suitable type
for the fuel available on site. The nameplate on the burner indicates for which type of fuel it
is designed.
excessive space in the refractory opening around the burner has been sealed with the supplied
ceramic material.
all items, packed in transit, are removed from combustion chamber.
boiler control thermostats are adjusted to suit system design ow temperature.
the limit and high/low stats are set in accordance with control details. See page 14.
the boiler relief valve setting is suitable for the system (The setting should be at least 0.5 bar
above the system pressure).
oil supply pressure and temperature is suitable.
for pressurised systems, an AAV is tted on each boiler.