3
2
Device Installation
Installing the SmartLogger Behind the Main Control Front Door of the Power Unit
3
Electrical Connections
Preparing Cables
3.1
Type Recommended Specifications
PE cable
Outdoor copper cable with a cross-sectional area of 4–6 mm
2
or 12–10 AWG
RS485 communications cable
Two-core or multi-core outdoor shielded cable with a cross-
sectional area of 0.2–2.5 mm
2
or 24–14 AWG
12 V input power cable Supplied with the solution package
Ethernet cable Supplied with the SmartLogger
MBUS cable (optional) Supplied with the SmartLogger
•
Connect cables in accordance with the installation laws and regulations of the country or
region where the project is located.
•
Before connecting cables to ports, leave enough slack to reduce the tension on the cables and
prevent poor cable connections.