Installing Options
Disconnecting the MAE from Power and Removing Cables
1. ____ Power off the MAE, then proceed in reverse order as for the installation:
2. ____ Remove the external cables, see “Step 3.1 - Connecting the MAE to a
7585” on page 1-11.
3. ____ Remove inter-machines cables, refer to “Step 5 - Connecting the MAE to
the 3746-9X0” on page 1-16.
4. ____ Remove the MAE from the controller expansion
5. ____ Remove the 8228 (if any) from the controller expansion, see “Installing
the 8228s” on page 1-16.
6. ____ Remove the brackets installed on the MAE and the hardware from the
controller expansion, see “Step 2 - Installing the MAE” on page 1-5.
7. ____ If installed, remove the second ac outlet distribution box.
Preparing the MAE for Shipment
1. ____ Pack the machine using the pack/unpack instructions.
2. ____ Pack the customer's parts and documentation in one package and label it:
"Customer Package".
3. ____ Pack other parts and all maintenance documentation in another package
and label it: "Maintenance Package". Hold for use by IBM Service
Representative.
4. ____ Coil all removed cables and store them alongside the machine.
5. ____ Complete the removal records according to existing procedures. Inform
the IBM Branch Office that the machines are ready for shipment.
Chapter 7. Removing or Relocating Your Multiaccess Enclosure 7-3