5
MEB & MEJ BARS 5200214 Rev. F
Installing High Voltage Cables
1. Route the high voltage cables attached to each static bar along the machine
frame or wall to the power supply.
2. Cable supports are used to guide the cables back to the power supply. All cables
must be kept a minimum of 1/4” away from machine frame and parts, walls
and ceilings. If this is not possible, encase cables in plastic insulating tubing
(available from Simco-Ion).
3. Install spring-loaded cable con-nectors on the free end of each cable, as
described on the enclosed SL instruction sheet.
4. Ensure that the power supply is de-energized, and then remove the protective
plastic plug from the power supply high voltage connection by gently prying
with an insulated screwdriver.
5. Insert the cable (with spring loaded connector attached) into the power supply
high voltage connection. Screw in the knurled plug to secure the cable.
NOTE! – FINGER TIGHTEN ONLY.
5. OPERATION
Before energizing any power supply:
1. Ensure that all power supplies are properly grounded.
2. Ensure that all static bars are properly grounded.
3. Ensure that all static bars have been properly located, positioned and installed.
After the above checks have been performed, simply energize each power supply to
operate the static neutralizing bars.