PRODUCT RECEIPT
Up to mod. SUPERAC 1045:
- boiler body without insulation (the box of the electric board, the
documentation, the mineral wool insulation and the ceramic fiber mattress to
seal the fissure of the burner nozzle, is placed into the boiler furnace)
- n°1 cardboard box containing the casing.
The SUPERAC 1220÷4070 boilers are delivered already insulated and cased.
The box of the electric board, the documentation and the ceramic fiber mattress
to seal the fissure of the burner nozzle, is placed into the boiler furnace.
Handle the boiler body using appropriate equipment using the lifting hooks of
the boiler upper part.
Due to ist heavy weight it should not be handled manually.
12
Position the superior covers (4) (5) on the boiler.
Before joining them together, prepare the control panel (6) as specified below
and fix it on the right superior panel as follows: extend the feeler capillaries,
make then pass through the cover hole and insert them in the wells located
near the delivery tube.
Then fix the set to the cover.
Then connect the upper covers, placing them at joint on the side covers.
6
5
4
3
2
1
21