EasyManua.ls Logo

Kingspan BioDisc BAx User Manual

Kingspan BioDisc BAx
13 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
012696
Installation Guidelines for
BioDisc Units BA, BAx, BB and NB
Kingspan Environmental Service Contact Numbers:
GB: 0844 846 0500
NI: 028 3025 4077
IRL: 048 3025 4077
Important
Once installed, the motor should be left on and running.
If there is delayed electrical connection or if there is no power
available to operate the unit, then the motor with gearbox
must be removed and stored in a dry environment.
The motor keeps dry by generating its own heat when
operating. In a non-functioning situation, water vapour can
enter the motor and cause corrosion.
The motor must not be left non-operational for a period of 7
days or more.
010086
SCP Wiring Diagram
Issue
Description
Date
07
CC1074
January 2013
Enclosed Document
Question and Answer IconNeed help?

Do you have a question about the Kingspan BioDisc BAx and is the answer not in the manual?

Kingspan BioDisc BAx Specifications

General IconGeneral
BrandKingspan
ModelBioDisc BAx
CategoryWater System
LanguageEnglish

Summary

Service Contact Numbers

Enclosed Document

Important Operational Notes

Motor Protection and Downtime Procedures

Ensure continuous motor operation. Protect from water and corrosion during downtime; avoid extended non-operational periods.

HEALTH AND SAFETY

Introduction

General Installation Guidelines

These guidelines represent best practice for installation; verify appropriateness for specific site conditions.

Handling and Storage Procedures

Handle units carefully to prevent damage. Ensure stability when lifting and use suitable webbing slings; avoid chains.

Site Planning Considerations

Consider discharge consent, planning approval, ground conditions, water table, soakaway tests, and access for servicing.

Installation - General

Pipework and Excavation Stability

Design pipework to minimize damage from differential movement. Support excavation side walls if they won't maintain a vertical wall.

Excavation Dewatering and Protection

Dewater excavations where water table is high or flooding is likely. Use polythene sheeting to prevent cement wash-out.

Unit Support and Backfilling

Ensure uniform support to avoid point loads. Use water for ballasting during back-filling; maintain water level during concrete pour.

Electrical Supply Requirements

Provide adequate electrical supply complying with regulations. Select cable and overload protection based on table data.

BioDisc Installation

Excavation and Bed Preparation

Excavate for unit, surround, and bed. Lay concrete bed appropriate for site conditions, possibly with hard-core sub-base.

Unit Placement and Levelling

Place unit on bed, ensuring no voids. Check and ensure unit is level end-to-end and side-to-side within tolerances.

Concrete Haunching and Chamber Filling

Haunch concrete around the base. Pour water into chambers to specified depth for back-filling.

Concrete Backfilling for Invert Depth

Back-fill according to site conditions. 1250mm invert depth units require concrete back-fill to within 500mm of ground level.

Wet Site Installation

Anchor Bars and Concrete Back-fill

Assemble anchor bars. Place concrete back-fill in 200mm increments, ensuring compaction and avoiding voids.

Water Ballasting During Backfilling

Fill tank with water simultaneously with backfill material to prevent flotation. Maintain water level within 200mm of concrete level.

Dry Site Installation

Backfilling Material for Dry Sites

Use pea shingle, sand, or other free-flowing granular material for back-filling up to outlet level.

Installation of the Capacitor

Control Panel Installation

General Control Panel Installation

Position control panel safely, not reachable from the unit. Installation by qualified electrician according to IEE regulations.

Mounting Frame Installation

Set frame legs in concrete base, ensuring stability. Maintain clearance from finished ground level to the panel bottom.

Control Panel Component Installation

Remove covers carefully. Feed power supply cables through glands and wire to terminal blocks as per guides.

Integral Discharge Pump Wiring

Feed discharge pump power cable through gland hole and terminate to specified connections (TB1) following Table 2.

Sludge Return Pump Wiring and Settings

Feed sludge return pump cable through gland hole and terminate. Set run and pause times for the pump using Table 3.

Chemical Dosing System Wiring

Feed dosing pump and probe cables through glands and terminate to specified connections (TB4, TB7) following Table 2.

Chemical Dosing Pump Settings

Set run and pause times for the chemical dosing pump using the switches as detailed in Table 4.

Loss of Rotation Alarm Installation

Feed alarm cable through gland hole and terminate to connections (TB5). Activate the alarm using switch 10.

High Level Alarm Installation

Remove link, feed float cable through gland hole and terminate to connections (TB6). Fix float bracket correctly.

Beacon Installation

Mount beacon up to 30m from panel. Feed beacon cable through gland hole and terminate to connections (TB8).

Completing the Installation and Power Up

Connect battery, check display for 'F1', turn on mains supply. Press reset button to clear display.

Control Panel Fault Codes & Fuses

Ancillary Equipment

Start Up Procedures

Pre-Service Inspection and Owner's Handbook

Recommend Pre-Service Agreement Inspection. Refer to Owner's Handbook for detailed start-up procedure.

Initial Unit Operation

Leave unit filled with water. Switch on motor and leave running, even without sewage feed.

Unit Operation Without Power

If no power, remove and store motor/gearbox unit in a dry environment until ready for operation.

Integral Pump Unit Connection Warning

Do not connect integral pump units to sewage supply without ensuring electricity is connected and unit is operational.

Related product manuals